Sunday, December 7, 2008

Locked Up



Internal Doors delivered & waiting to be hung

Timber Doors to Alfresco Area

Plastered!

Laundry
Ensuite: Doors- Parbury 'concept oak' & Vanity Top- Parbury 'pearl bisque'.
Powder Room: Doors- Parbury 'pearl bisque' & Vanity Top Parbury 'concept oak'.
Main Bathroom
Kitchen: cupboards in Parbury 'pearl bisque' with Caesarstone benchtops in 'linen'.


The Plasterers have been through & the cabinetmakers have been busy!
Loving my new kitchen already.
Skirting & Architraves delivered & ready to be installed.

Bricks on site, but not a Brick Layer in sight!


Our bricks have been on site for around 4 weeks now, but there's no sign of action in the brick-laying department as yet. We have chosen 'coco' bricks from the Boral Nuvo range.

We're Wrapped!


Thermal wrapping has been added and portico poles have been cemented in place.

Roof & Windows Added

Friday, November 14, 2008

Roof Trusses Added 10/11/08


Grey Water system & Trithor termite barrier visible at edge of slab.


Rumpus/Home Theatre to the left & Alfresco on the right (above).



Sunday, October 19, 2008

Boxing For Slab

Site Start

Under Construction...

So far to date, we have purchased our 1011m2 slice of Australia, with settlement occurring at 2:30pm Friday 12th September 2008.

We signed contracts to build our 29.7sq (living) home on Monday 9th September 2008 and have survived our 3 hour colour selection appointment on Monday 15th September 2008.

We have gone to site as scheduled Tuesday 7th October 2008!